Clients: Burkebro Inc., on Mosaic Transit Constructors' Finch West LRT project
Location: Finch West Station, Finch Avenue West and Keele Street, Toronto, Ontario
Completed: 2021 to 2024
Services: Structural steel inspection, shop and field weld inspection, Quality Verification Engineer (QVE), Certificates of Conformance
Finch West Station is the eastern terminus of the Finch West LRT, where the new line meets TTC Line 1 at Keele Street. Over four years of construction, HAL served as inspection and Quality Verification Engineer for the structural steel at the station. The work covered the temporary works that kept traffic and pedestrians moving, the permanent station entrance building, and the shoring of the pedestrian tunnel. Every stage was inspected against Mosaic's inspection and test plans and closed out with HAL's documentation.
PART 1 — KEEPING FINCH AND KEELE MOVING (2021)
Before the station could be built, traffic, pedestrians and buried utilities had to be carried over and around the excavation. HAL inspected the steel for the temporary works that made that possible: the temporary traffic bridge deck, the temporary pedestrian bridge, and the temporary utility supports at the west portal and under the pedestrian tunnel bridge. Inspections were carried out at the fabrication shop and on site, with weld inspection reports issued throughout. In February 2021, HAL confirmed that the installed steel was in general compliance with the project specifications, revised details and applicable codes.
PART 2 — THE STATION ENTRANCE BUILDING (2022–2023)
Between September 2022 and April 2023, HAL carried out periodic inspections of the structural steel for the station's main entrance building. Inspections took place at the fabricator's shop in Niagara and on site at Finch and Keele, against Mosaic's inspection and test plan for structural steel in buildings, with design changes to connection angles tracked as they were issued. In April 2023, HAL issued its inspection memo, photo appendix and Certificate of Conformance for the entrance building steel.
PART 3 — JACKING THE PEDESTRIAN TUNNEL SHORING (2024)
Late in construction, partial shoring was required for the pedestrian tunnel: steel struts and supports preloaded with hydraulic jacks onto micropiles, built to Mosaic's design. As Quality Verification Engineer, HAL:
-
Inspected the steel support members and struts against the design and shoring shop drawings
-
Witnessed the initial jacking in September 2024, recording the load at each jack before and after the plates were welded and the jacks released
-
Witnessed the follow-up load adjustments
-
Inspected the completed installation in October 2024
On October 25, 2024, HAL issued a Certificate of Conformance confirming that the shoring steel and the jacking process were in general conformance with the contract documents.
WHY IT MATTERS
On a P3 transit project, nothing is accepted until it has been inspected against its plan and signed off. Temporary works carry live traffic and people, permanent steel has to be documented for the owner, and remedial work like the tunnel shoring needs an independent engineer to confirm the design load was actually achieved. Having one QVE team across all three stages gave the contractor consistent, timely sign-off from the first temporary bridge to the final shoring.
OUTCOME
All the structural steel HAL inspected at Finch West Station, temporary and permanent, was found in general conformance. Each stage was documented with inspection reports, photo records and Certificates of Conformance, so it could be accepted and construction could keep moving.